Print Schedule Listing

To print a Job Schedule, click on Schedule in the shortcut menu, then click Print, then click Print Schedule Listing. Or, in the Job Schedule entry form, click the Print button, and select the Print Schedule Listing option.

The Job Schedule Listing report lists the date and duration of job items that have been scheduled in the Job Schedule entry form.

Using the prompts described below, you can print schedules for one or more jobs, and for one, or all Resources.

As you enter the actual start date and completion time of job items in the Job Progress entry form (discussed below), the job schedule listing will show how far behind or ahead of schedule each job item is.

The Print Job Schedule form has the following prompts:

Job Status:

Select the status of jobs to list in the schedule.

If you don't select a job status, the listing will include jobs with any status.

If you select a job status, the listing will only include jobs with that status.

Project:

Select the project of jobs to list in the schedule.

If you don't select a job project, the listing will include jobs in any project (or no project).

If you select a job project, the listing will only include jobs in that project.

Include Jobs:

Check the check box next to Jobs to include in the schedule listing.

If you don't check any boxes, the listing will only include the schedule for the current job (selected at the top of the screen).

If you select one or more jobs, the listing will include those jobs in the schedule listing with the current job.

Select Resource:

Select the Resource for whom to print a schedule, or "(All Resources)".

If you select "(All Job Resources)", the schedule will include items for all resources, sorted by date.

If you select a resource, the schedule will only include items scheduled for that resource.

Scheduled From:, To: 

You can select a range of dates for which to print the schedule.

The Scheduled From prompt defaults to the current date, but you can enter past dates to see past schedule dates.

The Scheduled To prompt defaults to the scheduled completion date, but you can enter dates previous to that to print less of the schedule

View button

Click View to view a print image of the report. This will display the report in the report viewer form.

Print button

Click Print to print the report.

Export button

Click Export to export the schedule data in a .csv file that can be imported into MS Project, or other MS Project compatible scheduling systems, such as Gantt Project.

Exit button

Click Exit to close the form.



The Job Schedule listing report has the following columns. Note: not all columns are visible, but appear under the conditions described below.

Start

The date on which the job item is scheduled to start.

Days

The number of days of work scheduled for the job item.

Hours

The number of hours of work scheduled for the job item.

End 

The date on which the item is scheduled for completion.

Critical items must be completed within the number of days in the "Days" column from the "Start" date. Non-critical items can start and complete any time after the "Start" date and before the "End" date.

For more information, please see the Critical Path Method scheduling topic.

Job

The last name of the job customer. This column appears when the multiple jobs are selected in the "Include Jobs" prompt.

Item

The name of the job item.

CP

An asterix (*) indicates the item is a critical path item.

Resource

This column displays the "short name" of the Resources assigned to the job item on the date displayed in the date column.

You enter schedule resources in the Resource Entry form, and you assign resources to schedule items in the Edit Estimate form, or in the Item Resource form that appears when you right-click on an item in the Edit Schedule form.

This column appears when the "(All Resources)" option is selected in the prompt for Resource.

Days Complete 

Days completed. You enter the number of days completed in the Job Progress entry form, or in the Item Resource form that appears when you right-click on an item in the the Edit Schedule form.

Days Behind 

This column shows the number of days the item is off schedule.

A positive number indicates that the job is behind schedule; a negative number indicates that the job is ahead of schedule.